圖133、About 2000m ³ Technical requirements for welding of LNG storage tank - Doer equipment

Classification:Forum PublishTime:2019-12-20 14:06:22

About 2000m ³ Technical requirements for welding of LNG storage tank


About 2000m ³ The welding technology of LNG storage tank generally specifies the selection of welding materials:


Selection of welding materials



Welders for welding shall hold valid certificates.


Pre welding inspection shall be conducted before welding, and the weld groove surface shall be cleaned.


Arc striking and test current on weldments are strictly prohibited, and arc striking plates shall be set


Welding process requirements:


Welding shall be carried out in strict accordance with the welding process instruction and welding process qualification.


Arc striking is not allowed on the surface of weldment, and there shall be no arc scratch and other defects on the surface of weldment.


During welding, the quality of arc starting and arc stopping shall be ensured. During arc stopping, the arc pit shall be filled, and the interlayer joints of multi-layer welding shall be staggered from each other.


During stainless steel welding, protective paste, chalk powder or lime powder shall be coated within 50mm on both sides of the welded junction to prevent fusion spatter from damaging the material surface.


After welding, the slag on the weld surface and nearby spatter shall be cleaned in time.


The welding procedure is shown in the figure below: