+86 512-81666096106,Preparation before construction of large atmospheric storage tank (2) - Doer equipment
Classification:Industry PublishTime:2019-11-07 13:39:20
Preparation before construction of large atmospheric storage tank (2)
Construction technology training: the technical training should be done well in the preparation stage of tank construction, as shown in the table below:
List of construction technology training:

Foundation acceptance: before the tank bottom plate is laid, the tank foundation shall be accepted. If it is found to be unqualified, it shall be handled in time. The quality standard of foundation acceptance is shown in the following table:

The foundation shall be provided with settlement observation points, which shall be recorded at the time of handover, and the observation points shall be remeasured and recorded.
Prev: 105,Preparation before construction of large atmospheric storage tank (1) - Doer equipment
Next: 180、Function and overview of air heated carburetor - Doer equipment
News
- 216、Advantages of Double Metal Full Capacity Tank … [2023-05-09]
- 215、Design principles for low-temperature storage … [2023-05-09]
- 214、Low temperature storage tank safety education … [2023-05-09]
- 213、Objectives of project construction management-… [2023-05-09]
- 212、Quality service advantages of Doer large low-t… [2023-05-09]
- 211、Advantages of Doer Large Low Temperature Stora… [2023-05-09]
- 216、Design scope of atmospheric and low-temperatur… [2023-05-08]
- 215、Process flow of low-temperature LNG storage ta… [2023-05-08]
- 214、Testing methods for low-temperature argon stor… [2023-05-08]
- 213、Performance Description of Low Temperature Eth… [2023-05-08]